• Building Program Timeline

     

     

    On March 18, 2008, Anderson School District One approved $85,750,000 referendum to improve school facilities for our students.

     

    The following is a building program timeline with the construction outline for each school.

     

    Palmetto High - New Field House

    Construction Began:                December 1, 2008

                Completed:                              August 2009   

     

    Palmetto High - 6 Classrooms, Weight Room, Cafeteria Expansion, Upgrade Security Systems, Weight Room, Athletic Bleacher – Softball/Baseball

    Design Phase:                          December 2008 – September 2009

                Bids:                                        November 2009

                Construction Begins:               January 2010

                Completed:                             August 2010

     

    Wren High - New Field House/Multipurpose Facility to Include Separate Practice Facility for Sports like Wrestling, Cheerleading, ect., and Public Restrooms, Replace Track Adding Lanes to Accommodate 4A Track Meet, Restroom Renovations in Original Building, Pave Additional Parking Areas, Upgrade Security

    Bids:                                        December 2008

                Construction Began:                January 2009

                Completed:                              August 2009

     

    Wren Middle - 10 Classrooms, Upgrade Security, Restroom Upgrades, Painting

                Bids:                                                     January 2009

                Construction Began:                            April, 2009

                Renovations Completed:                     August 2009

                Classroom Additions Completed:        December 2009

     

    Palmetto Middle - 10 Classrooms, Upgrade Security Systems, Restroom Upgrades, Painting of Building

                Bids:                                                    February 2009

                Construction Began:                            May 2009

                Renovations Completed:                     August 2009

                Classroom Additions Completed:        December 2009

     

    Concrete Primary - 10 Classrooms, Book Room, Storage Room, Assistant Principal’s Office, Kitchen, Cafeteria Expansion, Upgrade Security System, Upgrade HVAC, front lobby upgrade

                Bids:                                                   May 2009

                Construction Begins:                          June 2009

                Classroom Additions Completed:      April 2010
                Renovations & Kitchen Completed: August 2010
     

    Spearman Elementary - 8 Classrooms, New Cafeteria & Kitchen, New Restrooms for 3rd - 5th Grade Wing, Upgrade Security, Extend Car Lane/Renovations

                Bids:                                        August 2009

                Construction Begins:               September 2009
                Completion of Classrooms:     May 2010
                Renovations:                           December 2010
     

    Palmetto Elementary - 10 Classrooms, Book Room, Work Room, Upgrade Security, Front Lobby Upgrade, Extend Car Lane, Renovated Existing Building

                Bids:                                        September 2009

                Completed:                              August 2010

     

    Powdersville High – Build a New High School for 950 students on 45 acres on Powdersville schools’ site

                Site Bid Package:                     March 2009

                Bid:                                          May or June 2009

                Construction Begins:               July 2009

                Completion Date:                    June 2011

     

    Powdersville Middle – 8 Classrooms, Upgrade Security, new football/soccer practice field

                Bids:                                        October 2009

                Construction Begins:               December 2009

                Completed:                              August 2010

     

    Wren Elementary – 10 Classrooms, Book Room, Storage Room, Assistant Principal’s Office, Cafeteria Expansion, Upgrade Security, Front Lobby Upgrade, Extend Car Lane, New Bus Circle

                Bids:                                        July 2010

                Construction Begins:               September 2010

                Completion Date:                    July 2011

     

    Cedar Grove Elementary – 10 Classrooms, Book Room, Storage Room, Upgrade Security, Front Lobby Upgrade

                Bids:                                        October 2010

                Construction Begins:               December 2010

                Completion Date:                    July 2011

     

    Hunt Meadows Elementary, Powdersville Elementary, West Pelzer Elementary – Upgrade Safety and Security Systems
     
    All projects are on schedule and at present under budget.